Q1 business case·BCDF Stage 2 — Preliminary Business Case·Gateway Gate 1·2026
Preliminary Business Case: options analysis to a preferred option.
BCDF Stage 2 takes the substantiated need from the SBC and runs a structured options analysis — longlist to shortlist to a single reference project. Four decision axes were screened against real alternatives. Every axis selected the configuration now in the deal room; the preferred option is a behind-the-meter pilot at Swanbank, staged to the 800 MW program. Recommendation: proceed to a Detailed Business Case.
Options were screened on the binding constraint for sovereign compute — firmed power + grid headroom + a heat sink under one cooperative owner — not on rack availability. The longlist (do-nothing, colocation, greenfield, brownfield energy-precinct co-location) reduced to a shortlist on siting, then cooling, power, density and staging.
Options analysis — siting the decision that superseded the colo plan
Option
For
Against
Verdict
Do nothing
No capital at risk
Need unmet; QGOV defers AI or accepts offshore exposure
Rejected
Colocation (NEXTDC-class)
Fast to first rack; no construction risk
Rents someone else's power story — $/kW premium, no behind-the-meter energy, no heat-sink control, sovereignty diluted by the landlord's stack; caps below program scale
Rejected
Greenfield build
Full design control
Grid-connection queue in years; no existing firming; land, water, approvals from zero
Rejected
Swanbank brownfield
385 MW firm generation + 250 MW/500 MWh battery operational since Feb 2026; 1.2 GW connection with a commissioned 275 kV substation; purpose-built cooling reservoir; one QLD-government-owned landlord courting tenants; 11 km from Brisbane
Brownfield legacy (PFAS) to scope; terms not yet executed
Preferred
This selection is why the prior NEXTDC-colocation Series A page was superseded.
Each step built only when the demand stack underwrites it; capital never runs ahead of proven utilisation
Preferred option — the reference project
A ~2 MW, ~2,850-GPU behind-the-meter pilot at CleanCo's Swanbank Energy Precinct, closed-loop liquid cooled to the Cooling Water Dam, firmed battery-first — staged through 20 MW and 100 MW phases toward the 800 MW program on the same 1.2 GW connection. This is the reference project the DBC develops.