AloomU.au

Q1 business case·BCDF Stage 2 — Preliminary Business Case·Gateway Gate 1·2026

Preliminary Business Case: options analysis to a preferred option.

BCDF Stage 2 takes the substantiated need from the SBC and runs a structured options analysis — longlist to shortlist to a single reference project. Four decision axes were screened against real alternatives. Every axis selected the configuration now in the deal room; the preferred option is a behind-the-meter pilot at Swanbank, staged to the 800 MW program. Recommendation: proceed to a Detailed Business Case.

Options framework BCDF Stage 2 · longlist → shortlist

Options were screened on the binding constraint for sovereign compute — firmed power + grid headroom + a heat sink under one cooperative owner — not on rack availability. The longlist (do-nothing, colocation, greenfield, brownfield energy-precinct co-location) reduced to a shortlist on siting, then cooling, power, density and staging.

Options analysis — siting the decision that superseded the colo plan

OptionForAgainstVerdict
Do nothingNo capital at riskNeed unmet; QGOV defers AI or accepts offshore exposureRejected
Colocation (NEXTDC-class)Fast to first rack; no construction riskRents someone else's power story — $/kW premium, no behind-the-meter energy, no heat-sink control, sovereignty diluted by the landlord's stack; caps below program scaleRejected
Greenfield buildFull design controlGrid-connection queue in years; no existing firming; land, water, approvals from zeroRejected
Swanbank brownfield385 MW firm generation + 250 MW/500 MWh battery operational since Feb 2026; 1.2 GW connection with a commissioned 275 kV substation; purpose-built cooling reservoir; one QLD-government-owned landlord courting tenants; 11 km from BrisbaneBrownfield legacy (PFAS) to scope; terms not yet executedPreferred

This selection is why the prior NEXTDC-colocation Series A page was superseded.

Options analysis — cooling, power, density, staging

AxisAlternatives screenedSelectedWhy
CoolingAir (fails at ~80 kW) · evaporative (potable draw, discharge, PFAS interaction)Closed-loop direct-to-chip liquid to the Cooling Water DamZero potable water per token; no evaporative draw, no creek discharge; PFAS contained by construction
PowerGrid retail supply (wholesale + network exposure)Behind-the-meter firmed block, battery-first, gas transitionalBelow the ~$65/MWh QLD grid average; electricity <3% of revenue
Density20–40 kW air-cooled racks~80 kW liquid-cooled racksHalves hall footprint per MW; matches the loop
StagingBuild big first (100 MW+ day one)Gate-built staircase: ~2 MW → ~20 MW → ~100 MW → 800 MWEach step built only when the demand stack underwrites it; capital never runs ahead of proven utilisation

Preferred option — the reference project

A ~2 MW, ~2,850-GPU behind-the-meter pilot at CleanCo's Swanbank Energy Precinct, closed-loop liquid cooled to the Cooling Water Dam, firmed battery-first — staged through 20 MW and 100 MW phases toward the 800 MW program on the same 1.2 GW connection. This is the reference project the DBC develops.

Preliminary economics indicative · stabilised yr-1 · pre-financing

Installed GPUs (~25 racks @ ~80 kW, ~2 MW IT)~2,850
Annual revenue (~$2.35/GPU-hr · 85% utilisation)~$50M
EBITDA (~83% margin)~$41M
Build capex~$98M
All-in Stage-1 raise (all-equity worst case)~$116M
Simple payback · electricity share of revenue~2.4 yr · <3%

Stress-screened to $1.80/GPU-hr · 65% utilisation — remains EBITDA-positive, payback toward ~5 yr. Full grid in the financial model.

Preliminary risk register carried into the DBC with owners

RiskClassTreatment carried to DBC
Offtake not yet contractedCommercialTenancies over firmed-MW blocks; QWork Tenancy 01 anchor; executed tenancy an investment-decision condition precedent
Site terms TBC (lease, $/MWh, dam, connection)CommercialWave-1 workstream; all executed before the investment decision
PFAS legacy contaminationEnvironmentalClosed-loop contains by construction; scope signed with CleanCo's environmental team
Gas vs sovereign-clean narrativeReputationalBattery-first firming, gas transitional; auditable renewable path; no 100%-renewables claim
GPU price & availabilitySupplySupply agreement with delivery deadline, ramp pricing, pro-rata shortfall relief; vendor finance on the resaleable asset
Technology refreshTechnology4–5 yr depreciation; resale backstop; tight per-tranche generation
Single-site concentrationOperationalN-1 connection; program-scale redundancy addressed at Phase-1

Gateway position

GateGateway reviewWhat it testsOur productStatus
0Strategic assessmentService need substantiated — sovereign compute for QGOV & the regulated sectorSBCAddressed
1Preliminary evaluationOptions analysed; preferred option (Swanbank, closed-loop, staged) selectedPBCAddressed
2Business caseDetailed evidence — economic, financial, commercial, risk, managementDBCIn progress
3Contract award / investment decisionExecuted terms + tenancy; Stage-1 capital committed (FID)DBCPending — CPs open
4Readiness for servicePilot energised; switch cut over to Swanbank silicon; dashboard → productionWave 2Future
5Benefits realisationUtilisation proven; Customer #2 live; QGOV value deliveredWave 3–4Future
Gate 1 — addressed. The preferred option is selected and the business justification holds. Recommendation: proceed to the Detailed Business Case.